Tuesday, September 4, 2012

Plot holders of Sector-52, HUDA, Gurgaon, Haryana fail to take up fight against enhancement.


There seems to be a ray of hope for HUDA plot holders in Gurgaon who are seeking relief from atrocious enhancement levied by HUDA, Gurgaon. As the residents of Sector-27 & Sector-28, HUDA Panchkula, Haryana show them the way.

Residents of HUDA Sector-27 & Sector-28, Panchkula, Haryana were imposed with similar enhancements of Rs.3098.16 per Sq.yd & Rs.4646.49 per sq.yd and they sensed that the enhancement imposed upon then was grossly non maintainable.

Residents of Sector-27 & Sector-28, HUDA Panchkula, Haryana got together and filed their case against HUDA for non maintainable enhancement in the Hon’ble High Court of Punjab & Haryana at Chandigarh through their Ld Counsel Sh A.S Tewatia, who as a through professional attained speaking order for HUDA Administrator to form a committee and report within 2 months.

On this a committee was formed and HUDA issued  No.HUDA-CCF-Acctt-II-2012/11347-48, dated 28/3/2012 for Sector-27, Panchkula, Haryana & No.HUDA-CCF-Acctt-II-2012/11349, dated 28/3/2012 for Sector-28, Panchkula, Haryana where in HUDA officially retracted and said that the recovery rate for Sector-27, Panchkula, Haryana has been worked out to Rs.1903.76 per sq.yd against the previous recovery rate of Rs.3098.16 per Sq.yd. and for Sector-28, Panchkula, Haryana recovery rate has been worked out to Rs.2495.34 per sq.yd against the previous recovery rate of Rs.4646.49 per sq.yd for general category

Now in January 2012 HUDA, Gurgaon  issued orders imposing the enhanced cost for Sector-27, 28, 42,43, 51 & 52 Gurgaon as under:-

1
Sector-27
Rs 4993.77 per sqyds       (1st Enhancement)         
2
Sector-28
Rs 4716.96 per sq yds      (1st Enhancement)                     
3
Sector-42
Rs 4951.61 per sqyds       (1st Enhancement)                   
4
Sector-43
Rs 5185.00 per sqyds        (1st Enhancement)                  
5
Sector-51
Rs 4666.06 per sqyds        (3rd  Enhancement)                  
6
Sector-52
Rs 4215.89 per sqyds        (3rd  Enhancement)                 

   












Since the Sector-27, 28, 42 & 43 have fair number of residents and they have taken up their fight against the enhancement to courts at their own level and it seems that they will get justice soon.

Sector-51 & 52 has faced the maximum brunt of enhancement as it is facing 3rd enhancement where as other sectors are having their 1st enhancement. Despite loosing precious money the residents of Sector-51 & 52 seems to be losing the fight as it does not have much residents living in these 2 sectors.

An effort was made few months back to form a forum by the residents of Sector-52 but nothing could be achieved. Now a fresh endour has been made same counsel Sh A.S Tewatia (who got the relief for the residents of Sector-27 & 28, HUDA, Panchkula, Haryana) has been finalised.

It is further clarified that only those whose name features in petition will be benefited by the Court’s relief because HUDA does not provide blanket relief (HUDA has extended relief in Panchkula to only those whose name were in petition)

It is the only time where in you can be a part of petition and save your hard earned money.

Those who wish to participate in the petition against HUDA can revert at pankaj@easyghar.com or else call Pankaj at +91-9899740003



ORDERS FOR SECTOR-27, PANCHKULA

HARYANA URBAN DEVELOPMENT AUTHORITY, PANCHKULA.

No.HUDA-CCF-Acctt-II-2012/11347-48                                          Dated :28/3/2012

To 
The Estate Officer,
HUDA, Panchkula.
  
Subject : Revised Recovery of 1st  enhancement and 2nd  (new) enhancement in respect
of sector-27, Panchkula.

Ref:- This is in-continuation of this office memo.no.HUDA.CCF.Acctt-II-2010/ 24564-69
dated 15.07.2011.

It is intimated that in compliance of the orders of Hon’ble Punjab and Haryana High Court in CWP No.18681/2011 (O&M) the representation from Joint Action Committee of Sector 25 to 28, Panchkula was received against the recovery of enhancement of sector-27, Panchkula. The representation of the Joint Action Committee was examined and meetings were also held with the representative of Joint Action Committee. The Joint Action Committee intimated that there is difference in the area and amount paid to land owners on which the enhanced compensation had been worked out then the area existed at site. The STP, HUDA and DTP, Panchkula, were asked to verify the actual area. LAO, Panchkula and Sr.A.O., Panchkula O/o Administrator, HUDA, Panchkula were asked to reconcile the payments. After reconciliation the detail of area and payments by CTP/DTP and LAO/Sr.A.O., Panchkula, it was decided to make the corrections in the rate of recovery of enhanced compensation on the basis of actual area, actual payments detail and speaking order passed in compliance of the order of Hon’ble Punjab and Haryana High Court in CWP No.18681/2011 (O&M).

Accordingly the recovery rate has been worked out to Rs.1903.76 per sq.yd against the previous recovery rate of Rs.3098.16 per Sq.yd. for general category in respect of Sector-27, Panchkula.

This recovery will be affected from the date of issue of original notice with the following stipulations:-
(i)     The allottees who have paid the extra amount due to decrease in the rate of recovery will beallowed interest @15% p.a. on the excess amount paid by them. 
(ii)    The allottees who have not paid/ partly paid of enhanced compensation, the amount will be charged the interest @15% per annum on the revised rates from the date of issue of original notice.

On the basis of further payments made to the land owners by the LAO, Panchkula, the second recovery rate of enhanced compensation works out to Rs.162.33 per Sq.yd. for General category. The recovery of which notices may be issued within 15 days. The extra amount paid by the allottees of 1st enhancement along with the interest may be adjusted against the 2nd enhancement and excess amount, if found, thereafter may be refunded.

You are, therefore, requested to issue the revise notices of recovery of 1st enhancement and issue the notices of 2nd  enhancement as per above decision. The copy of revised calculation of 1st enhancement and copy of 2nd enhancement are enclosed herewith. Any amount of enhancement compensation paid thereafter will be recoverable from the allottees.


                                 
(Surjeet Singh)
                                   Accounts Officer,
                                                 for Chief Administrator,
                                                                                                                                                                                 HUDA, Panchkula


Endst.No.HUDA.CCF.Acctt.-II/2012/                                               Dated :

A copy of above is forwarded to the Administrator, HUDA, Panchkula for information and necessary action.


                                (Surjeet Singh)
                                Accounts Officer,
                             for Chief Administrator,
                                                                   HUDA, Panchkula  





ORDERS FOR SECTOR-28, PANCHKULA

HARYANA URBAN DEVELOPMENT AUTHORITY, PANCHKULA.

No.HUDA-CCF-Acctt-II-2012/11349                                              Dated :28/3/2012

To 
The Estate Officer,
HUDA, Panchkula.
  
Subject: Revised Recovery of 1st  enhancement and 2nd (new) enhancement in respect
of sector-28, Panchkula.

Ref:- This is in-continuation of this office memo.no.HUDA.CCF.Acctt-II-2010/ 24564-69
dated 15.07.2011.

It is intimated that in compliance of the orders of Hon’ble Punjab and Haryana High Court in CWP No.18681/2011 (O&M) the representation from Joint Action Committee of Sector 25 to 28, Panchkula was received against the recovery of enhancement of sector-28, Panchkula. The representation of the Joint Action Committee was examined and meetings were also held with the representative of Joint Action Committee. The Joint Action Committee intimated that there is difference in the area and amount paid to land owners on which the enhanced compensation had been worked out then the area existed at site. The STP, HUDA and DTP, Panchkula, were asked to verify the actual area. LAO, Panchkula and Sr.A.O., Panchkula O/o Administrator, HUDA, Panchkula were asked to reconcile the payments. After reconciliation the detail of area and payments by CTP/DTP and LAO/Sr.A.O., Panchkula, it was decided to make the corrections in the rate of recovery of enhanced compensation on the basis of actual area, actual payments detail and speaking order passed in compliance of the order of Hon’ble Punjab and Haryana High Court in CWP No.18681/2011 (O&M).

Accordingly the recovery rate has been worked out to Rs.2495.34 per sq.yd against the previous recovery rate of Rs.4646.49 per sq.yd for general category and Rs.367.50 per sq.yd. against the previous recovery rate of Rs.684.31 per Sq.yd. for EWS category in respect of Sector-28, Panchkula.  

This recovery will be effected from the date of issue of original notice with the following stipulations:-
(i)     The allottees who have paid the extra amount due to decrease in the rate of recovery will be allowed interest @15% p.a. on the excess amount paid by them.   
(ii)    The allottees who have not paid/ partly paid of enhanced compensation, the amount will be charged the interest @15% per annum on the revised rates from the date of issue of original notice.

On the basis of further payments made to the land owners by the LAO, Panchkula, the second recovery rate of enhanced compensation works out to Rs.212.78 per Sq.yd. for General category and Rs.31.34 per sq.yd. for EWS category. The recovery of which notices may be issued within 15 days. The extra amount paid by the allottees of Ist enhancement along with the interest may be adjusted against the 2nd enhancement and excess amount, if found, thereafter may be refunded.

You are, therefore, requested to issue the revise notices of recovery of 1st enhancement and issue the notices of 2nd enhancement as per above decision. The copy of revised calculation of 1st enhancement and copy of 2nd enhancement are enclosed herewith. Any amount of enhancement compensation paid thereafter will be recoverable from the allottees.

                              
 (Surjeet Singh)
                                   Accounts Officer,
                                for Chief Administrator,
                                                                                                                        HUDA, Panchkula

Endst.No.HUDA.CCF.Acctt.-II/2012/                                                           Dated :

A copy of above is forwarded to the Administrator, HUDA, Panchkula for information and necessary action.


                                (Surjeet Singh)
                                Accounts Officer,
                             for Chief Administrator,
                                                                   HUDA, Panchkula